1. Consent for excavating in a road by a private party

(under Section 109 of the New Roads and Street Works Act 1991)
Permits and Consent Rates as of 1/4/08
1.1 Excavation not involving installation of private apparatus £82
1.2 Excavation for installation of a private apparatus, classed as Minor Works (one inspection included) £161
1.3 Excavation for installation of a private apparatus, classed as Major Works up to one inspection unit (3 inspections included) £227
1.4 Cost of additional inspection to 1.2 or 1.3 £25
1.5 Additional charge to 1.3 per additional inspection unit £75
The above fees are approved nationally  

top of page2. Road Occupations

Note: As from 1 October 2008, new legislation comes into effect introducing fixed penalties for unauthorised road occupations. The penalty will be £120 reduced to £80 for prompt payment. Consent will still be required if the occupation is to continue and the normal permit fees will apply in addition to the fixed penalty.

Permits and Consent Rates as of 1/4/08
2.1 Scaffold for a continuous period up to one month:
a) Less than 25 metres long £80
b) 25 metres or over £110
c) Each subsequent month £44
2.2 Scaffold – extension of original permit up to 1 month
a) Under 25 metres £70
b) 25 metres or over £100
2.3 Mobile tower scaffold (erected and dismantled daily) £17/day
£32/week
2.4 Crane permits, occupation of a road for up to 1 week £70
2.5 Temporary traffic signals occupation of a road up to 7 days £32
2.6 Builders Skip up to 7 days £21
2.7 Building Materials up to 7 days £21

top of page3. Temporary Traffic Orders

Permits and Consent Rates as of 1/4/08
3.1 For planned works up to 5 days £300
3.2 For planned works in excess of5 days but not more than 18 months £540
3.3 For any extension to a temporary restriction where permissible £300

4. Vehicular Access

Permits and Consent Rates as of 1/4/08
4.1 Application for a new vehicular access from an unclassified road where formal Planning Consent is not required. Charge per application £32
4.2 Application for keep clear marking (elongated "H") at private access. £210

top of page5. Road Status Enquiry Outwith Formal Property Enquiry System

Permits and Consent Rates as of 1/4/08
5.1 Application for information for road classification from the statutory list of public highways. Charge per application £25

6. Printing/Photocopying Charges

Charges for photocopying/printing documents for the public. Single sided copies:

Paper Size Rates as of 1/4/08
A4 25p
A3 50p
A2 £11
A1 £13
AO £19

 

 